The paving of two segments of Gypsy Lane will begin on June 13.
The first is West Gypsy Lane Road from Sand Ridge Road to approximately 125 West Gypsy Lane Road and the second is East Gypsy Lane Road from the east side of the I-75 overpass to South Dunbridge Road.
The contractor plans to begin milling on June 13 and will begin a full closure of West Gypsy Lane Road between Sand Ridge Road and Rudolph Road on June 17. This full closure is expected to last two weeks. Following the full closure, work will progress on the remainder of Gypsy Lane Road with one lane of travel blocked for construction. Construction flaggers will direct drivers through the work zone.
The project is contracted to be completed by the end of October.